Which Primavera P6 files does Chronaxis read?
XER exports from Primavera P6 Professional and EPPM. Load the baseline and each programme update; Chronaxis checks every file for open ends, hard constraints, negative float, out-of-sequence progress and invalid dates before the analysis runs.
Which delay analysis methods are used?
A contemporaneous windows analysis (AACE 29R-03 MIP 3.3 and 3.4 with a half-step to separate progress from revisions), cross-checked with a Time Impact Analysis (MIP 3.7) using fragnets. The approach follows the SCL Delay and Disruption Protocol, 2nd edition.
Does my project data leave my computer?
No. Programmes, contracts and correspondence are read and analysed on your own computer. Nothing from your project is uploaded to us. The only online step is a short licence check.
Can I edit the claim report?
Yes. The report is a normal Word document with styles, a table of contents and numbered sections, so you can add your own wording, logos and exhibits. Every allocation decision can also be changed inside the software, and the reason is printed in the report.
Does it work with FIDIC and bespoke contracts?
Yes. Chronaxis reads the Conditions of Contract as PDF or Word and finds the extension of time, notice and delay damages clauses in FIDIC 1999, FIDIC 2017 and bespoke forms. You confirm the clauses and notice periods before they are used.
What do I need to run it?
A Windows 10 or 11 computer. Microsoft Word or LibreOffice is used to create the PDF bundle. A macOS version is planned.
Is there a free trial?
Yes, 14 days with every feature. Outputs made during the trial carry a watermark, so they cannot be submitted until you subscribe.
How can I pay?
By Visa, Mastercard, American Express, Apple Pay, Google Pay or PayPal through a secure checkout. Companies on yearly plans can also pay by invoice and bank transfer. Every payment comes with a tax invoice, and VAT or sales tax is added where it applies.
Can I cancel at any time?
Yes. Cancel in one click and your plan stays active until the end of the period you paid for. Founder pricing stays with your subscription for as long as it runs.
Do you offer team and company licences?
Yes. Each licence covers one computer and can be moved when you change machines. For several users, a yearly invoice or a custom agreement, write to hello@chronaxisapp.com.